Cost Estimation Guide: Renovating a Type 36 House into a 2-Story Home in Indonesia (2026)
Konstruksi

Cost Estimation Guide: Renovating a Type 36 House into a 2-Story Home in Indonesia (2026)

Rian Hendrawan, IAIAugust 24, 2026 2 mnt read

"How much does it really cost to renovate a type 36 house into a 2-story home in 2026? Read exact breakdowns for foundations, materials, and labor models."

Executive Summary (2026 Renovation Guide)

  • Total Estimated Cost: **IDR 125,000,000 – IDR 175,000,000** (Adding ~36 to 40 sqm on the 2nd floor).
  • Turnkey Contractor Rate: **IDR 3,500,000 – IDR 4,500,000 / sqm** (Includes labor, mid-tier materials, and finishing).
  • Structural Requirements: 10 – 12 **Cakar Ayam** foundation footings (1.5m depth), SNI D12 steel rebar, and 0.75mm Bondek floor decking.
  • Mandatory Permits: Building Approval (**PBG**) issued via the official SIMBG portal.

Renovating a type 36 house into a 2-story home is the most logical solution for growing urban families in Indonesia. Given the escalating price of land in metropolitan areas, expanding vertically is significantly more cost-effective than purchasing a new plot.

This comprehensive guide details the technical specifications, real material costs, labor models, and building permit procedures updated for 2026.

---

1. Structural Foundation & Concrete Floor Decking

Type 36 homes built by developers are generally structured for single-story loads. Converting to a two-story home requires **structural reinforcement** using "Cakar Ayam" footplate foundations at every primary column location.

Cakar Ayam Foundation and Steel Reinforced Concrete Column

Figure 1: Steel rebar reinforcement for earthquake-resistant 2-story house foundation in Indonesia.

Structural Foundation Cost Breakdown (12 Cakar Ayam Points):

Structural Component Material Specifications Est. Cost (IDR)
Cakar Ayam Excavation & Footings D12 SNI Rebar, 60x60 cm Footplate, 1.5m Depth IDR 18,500,000
Columns & Ring Beams K-225 / K-250 Concrete, 8mm Stirrups IDR 16,000,000
2nd Floor Decking (Bondek System) 0.75mm Bondek + M8 Wiremesh + Ready Mix Concrete (12cm thickness) IDR 23,500,000
Subtotal Primary Structure Cost IDR 58,000,000
---

2. Material Breakdown for Walls, Roof & Finishing

Renovated 2-Story Type 36 House Interior Design

Figure 2: Modern 2nd floor interior featuring high ceilings and optimized natural ventilation.

Finishing Material Cost Breakdown (~36 sqm added area):

Work Item Material & Volume Details Est. Cost (IDR)
Autoclaved Aerated Concrete (AAC/Hebel) Walls 7.5cm Hebel Blocks, Thin-bed Mortar, Exterior Paint IDR 22,000,000
Roof Structure & Metal Tiles Light Steel Trusses (C75.75 SNI) + Sand-coated Metal Roof Tiles IDR 17,500,000
Granite Tile Flooring 60x60 cm Polished Granite Tiles IDR 13,500,000
Gypsum Ceiling & Framing 9mm Gypsum Board + Galvalume Hollow Framing IDR 9,000,000
Aluminum Frames & Doors/Windows 3-inch Aluminum Framing + Panel Doors & Windows IDR 12,500,000
Electrical & Plumbing Works Eterna 2.5mm Wiring, Outlets, 2nd Floor Bathroom Fixtures IDR 14,500,000
Subtotal Finishing Material Cost IDR 89,000,000
---

3. Labor Models: Full Turnkey vs Labor Only vs Daily Wages

Labor Model 2026 Average Rate Advantages Disadvantages
Full Turnkey (Contractor) IDR 3.5M – 4.5M / sqm Bound by formal contract; hassle-free procurement and guaranteed schedule. Slightly higher cost (10-15% contractor profit margin).
Labor Only Contractor IDR 1.1M – 1.4M / sqm Full control over material purchasing and quality selection. Requires active owner participation in material supply management.
Daily Wage Workers Master: IDR 190k-220k/day
Assistant: IDR 130k-150k/day
Highly flexible for minor fixes or staged renovation. Risk of project delays if not strictly supervised daily.